LATEST NEWS
Trade Contracting
January 19, 2012
Toronto 2015 Pan Am Games construction off track, says lobbyist
Construction plans and contracts for the 2015 Pan Am Games are woefully bloated and running behind schedule says the man who helped bring the event to Toronto.
But the red flags from former Olympian sailor Paul Henderson, a key figure in both the failed Toronto Olympic bid and the successful Pan Am Games, are being shrugged off by Infrastructure Ontario (IO) while the consensus in the construction industry is that it’s a yellow flag, if anything.
In a letter to Premier Dalton McGuinty, Henderson says the scope of the Games; their attendant “soft costs” such as policing and the infrastructure required have either been under-estimated or overblown and is predicting a disaster unless swift action is taken now.
Related:
Construction begins on Toronto Athletes’ Village for 2015 Pan Am Games
Dundee Kilmer Development to build 2015 Pan Am Games Athletes’ village in Toronto
Infrastructure Ontario invites three teams to bid on Toronto 2015 Pan Am games facilities
“The escalation, as a direct cost to the taxpayer in the budget, could well be from $1.4 billion to over $2.5 billion if all costs are added in,” he wrote.
“It will approach $4 billion if the Athletes’ Village is also added to the total outlay. Although some of the costs of the Athletes’ Village may be recoverable it should be noted that the Vancouver 2010 Village had a major deficit.”
He also says ongoing maintenance and operating costs could run $100 million a year for the planned installations and that some hard thinking has to be done now.
Henderson also sounded the alarm over the lack of contracts being signed for construction.
“It is over two years since Toronto was awarded 2015 Pan and Parapan Games,” he said.
“No firm contracts have been signed with either the various construction consortia or with the stakeholders who represent the many levels of taxpayers’ dollars that will fund and operate the multitude of venues.”
Ontario General Construction Association president Clive Thurston, however, said his members aren’t unduly worried.
“I would say its business as usual,” he said.
“The process has only just begun and the only thing decided, really, is the Athletes’ Village,” added Thurston.
“I’ve not heard any negativity from the members, we’re in touch with Infrastructure Ontario and the process is proceeding so we’re not worried.”
Toronto Construction Association president John Mollenhauer was similarly nonplussed but said there is some buzz among members that they’d like to see traction.
“There’s lots of talk but it is early days,” said Mollenhauer.
“I wouldn’t describe it as a public outcry, they just want to get going but that’s the nature of the construction industry. Contractors often find they end up with too little time at the end of project and blame it on taking too long at the start.”
So far Henderson’s warnings and suggestions to stop reinventing the wheel in the design and construction of facilities and to double up usages of venues, instead of permanent swimming pools and other structures, and to build temporary structures, have not prompted any reaction at Queen’s Park, except among opposition MPPs looking to sling mud at the government.
With Ontario running a $16 billion annual deficit and carrying $241 billion debt, it can ill afford to get mired in cost over runs for the Games but IO insists everything is under control and that Henderson’s numbers are “outdated.”
An IO spokesman referred further question to TO2015 which responded with a written statement:
“TO2015 is working diligently with the funding partners and within the $1.4 billion budget established in 2010. TO2015’s business plan is currently in review with the federal and provincial governments. Recent cost escalation accusations are inaccurate and unfounded. Given the investment, profile and scope of this project, there is a rigorous process in place to ensure value and efficiency across all facets of the plan.”
| MOST POPULAR STORIES |
- Where does labour law stand on ladder safety?
- Stakeholders react to Ontario College of Trades proposed membership fees
- Cliffs Natural Resources to invest $3.3 billion in Ring of Fire
- Toronto studies construction of new islands
- PCL Constructors works on Humber River Regional Hospital in Toronto
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 455 projects with a total value of $1,378,405,540 that Reed Construction Data Building Reports reported on Thursday.
COMMERCIAL OFFICE BUILDING, RETAIL
$55,000,000 Ottawa ON Negotiated
TOWNHOUSE AND CONDOMINIUM APARTMENT DEVELOPMENT
$43,000,000 Clarington ON CANCELLED/ DEFERRED
$23,000,000 Ottawa-Carleton Reg ON Tenders
| CURRENT STORIES |
- EllisDon to build performing arts centre for Queen’s University in Kingston, Ontario
- Historic Burlington, Ontario railway station to be moved
- Widespread opposition to Ontario College of Trades membership classes
- The hunt for environmentally friendly cement continues with Michigan State University research on portland cement
- Safety training today builds safety leaders of the future, says IHSA
- Denis Dixon new Professional Engineers Ontario president
- University of Windsor design competition winners announced
- Construction material costs “took a breather” in April: Associated General Contractors of America
- VIDEO: Highlights from the May 18 Daily Commercial News
- VIDEO: Common ladder safety errors in construction
- Electrical Worker Crushed
- High School Construction
- Victoria bridge inches closer to construction
- Collapse injures worker at Commonwealth Stadium
- Panel appointed to oversee hearings into B.C. mine project
- Bockstael celebrates 100 years
- More work needed to protect flaggers
- Co-founder of ATCO announces his intention to step down as chair
- SNC-Lavalin hit with $1.5 billion class action lawsuit
- PST returns to British Columbia
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Economic Nuggets - May 15, 2012 (May 14, 2012)
- Canada Rode a Second Consecutive Month of Strong Job Gains in April (May 11, 2012)
- U.S. Employment Rose by a Mediocre 115,000 in April (May 4, 2012)
- More