DCN ARCHIVES

September 3, 2010

Project progress

Construction continues on Woodgreen Community Housing development in Toronto

WILLIAM CONWAY/PROGRESS PHOTOGRAPHY

Construction continues on the Woodgreen Community Housing project in Toronto. Struct-Con Construction Ltd. is general contractor of the eight-storey, 40-unit building. Completion is scheduled for January 2011.

The owner is Woodgreen Community Housing and the project was designed by Levitt Goodman Architects.

Consultants are: Halsall Associates Ltd. (structural) and Jain & Associates Ltd. (mechanical/electrical).

Subcontractors include: Vision Excavating; Pro Caissons; Blaze Contracting (formwork); Gilbert Steel Ltd.; Innocon Inc.; Target Drywall; Metrin Mechanical; Elux Electric; Eileen Roofing; and Kone Inc. (elevators).

Print | Email | Comment

MOST POPULAR STORIES
TODAY’S TOP CONSTRUCTION PROJECTS

These projects have been selected from 326 projects with a total value of $2,707,501,216 that Reed Construction Data Building Reports reported on Friday.

RAPID TRANSIT SYSTEM UPGRADES

$800,000,000 Waterloo Reg ON Prebid

SOLID WASTE FACILITY

$235,700,000 Clarington ON Negotiated

CONDOMINIUM APARTMENT BUILDING

$87,000,000 North York ON CANCELLED/ DEFERRED

Daily Top 10

CURRENT STORIES
ALEX’S ECONOMICS BLOG

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.

TODAY’S TOP JOBS

Chief/Senior Estimator
Ontario-Brampton

Inside Sale Representative
Ontario-Markham

Branch Manager
British Columbia-Surrey

Contracts Estimator & Project Coordinator
Ontario-Etobicoke

Structural Engineer
Ontario-Toronto

Manager Maintenance & Engineering Services
Ontario-Oakville

Supervisor
Ontario-Etobicoke

Estimator
Ontario-Etobicoke

Estimating Coordinator (10-804)
Alberta-Edmonton

Project Administrator
Saskatchewan-Saskatoon

More jobs 

myJobsite.ca

Your gateway to
the top careers
in construction
and design