LATEST NEWS
June 11, 2010
Canadian Construction Association meeting
Contractors warned of LEED liability
Regina
Canadian contractors need to be aware of the risk factors associated with the U.S. Green Building Council’s Leadership in Energy & Environmental Design (LEED) rating system, says a leading construction lawyer.
“The primary risk factor arises out of the fact that LEED certification is issued by a third party and a contractor may have little or no ability to manage that risk,” said Geza Banfai, a partner in Heenan Blaikie’s Infrastructure and Construction Litigation practice group.
Several problems can arise, he said during a recent meeting of the Canadian Construction Association in Regina.
“The first is that the certificate will not be issued at all by the third party, due to no fault of the contractor,” he said.
“The second is the certificate is going to be delayed. I understand that it is not unusual to have a LEED certificate issued weeks, if not months, after substantial performance.”
If the contractor has unwittingly entered into an agreement that holds up payment pending LEED certification, the contractor may have to finance this payment for an extended period of time.
If the contractor has assumed that risk, then the contractor may be liable for the damage sustained by others, Banfai said.
Also, the LEED certificate may be withheld under circumstances where the contractor had nothing to do with the problem.
“The key for the contractor is to carefully review the contract with the owner to make sure he has not unwittingly assumed these risks,” said Banfai. “For example, by promising that a LEED certificate is going to be issued by guaranteeing that result.”
Construction lawyer Harvey Berman said the first reported “green lawsuit” occurred in 2008 and involved the Captain’s Galley Luxury Condominiums in Crisfield, Maryland.
The developer was seeking LEED silver certification for its $7.5 million building and $635,000 in tax credits, which were tied to achieving the certification.
The contractor made the mistake of filing a lien and then suing the developer to obtain payment on a relatively small unpaid sum.
The developer then countersued the contractor for $1.3 million, claiming that the contractor was responsible for the developer’s failure to achieve the LEED certification and the loss of tax credits.
The developer claimed that the contract required that the contractor construct an environmentally sound “green building” in conformance with a “Silver Certification Level according to LEED. It also alleged that the contractor was nine months late in completing the project.
Berman, a partner in the Ann Arbor office of the law firm Bodman LLP and is head of the firm’s Construction Law practice, said the contract did contain a waiver of consequential damages.
However, the contract documents attached to the developer’s counterclaim contained no provisions limiting the contractor’s liability relating to any “green building” aspects of the project, did not discuss the role of the developer or the design/construction team regarding obtaining LEED certification, and did not discuss the LEED process or the effect of a project delay on the attainment of tax credits.
The case was settled in 2008 and the terms of the settlement were not made public.
The LEED program, which builders and property owners enter into voluntarily, certifies that a building is constructed in ways that help the environment, by saving energy, for example. LEED currently certifies existing buildings, commercial interiors, core and shell projects, neighborhood development (in pilot), and schools, healthcare, and retail projects.
| MOST POPULAR STORIES |
- How to suspend a 13-storey tower over a century-old four-storey structure
- Toronto Maple Leaf Gardens time capsule included construction details of arena
- Harley Davidson to roar into Quebec, with $15-million franchise headquarters under construction
- Steel hurdles for Aga Khan Museum build
- Caterpillar dispute a factor in CAW-CEP union merger talks
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 326 projects with a total value of $2,707,501,216 that Reed Construction Data Building Reports reported on Friday.
$800,000,000 Waterloo Reg ON Prebid
$235,700,000 Clarington ON Negotiated
CONDOMINIUM APARTMENT BUILDING
$87,000,000 North York ON CANCELLED/ DEFERRED
| CURRENT STORIES |
- National Research Council web wind tool helps with roof design
- Carillion Canada progresses on Ontario Coroner’s building in Toronto
- Benson Steel faces transport challenge on Toronto Yorkdale Mall construction project
- Knowing the bid rules essential for contractor success
- GDP down 0.1 per cent in November: Statistics Canada
- Ontario labour blitz to focus on musculoskeletal disorders
- Brazilian officials allege illegal construction in Rio de Janeiro high-rise building collapse
- Keeping it local in Lonsdale
- "Jobless boom" hits Saskatchewan
- Transmission line will generate shortages
- Fate of glass bridge not yet decided
- Why 45 days are important in the Builders Lien Act
- Construction and design modifications can promote elderly independence
- Inspired thinking highlights this year's Buildex Vancouver
- Industry to discuss changes in procurement
- The Living Building Challenge
- Getting a bigger bang with Building Information Modeling
- Come Say Hello to the Journal of Commerce
- Construction industry safety myths debunked in seminar
- A look at the challenges of smart structural reconstructions
- A look at the challenges of smart structural reconstructions
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 2) (January 12, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 1) (January 11, 2012)
- More








