May 29, 2010
FEATURE | Steel
HALSALL ASSOCIATES
Tower South Elevation at Algonquin Centre for Construction Excellence at Ottawa’s Algonquin College.
Algonquin Centre for Construction Excellence getting new $77-million home
With a fast-paced schedule designed to meet the Infrastructure Stimulus Funding program’s March 2011 deadline and a desire to achieve LEED Platinum, composite steel was the building material of choice for the Algonquin Centre for Construction Excellence at Ottawa’s Algonquin College.
Designed by Diamond and Schmitt Architects Incorporated and Edward J. Cuhaci and Associates, the $77-milllion, 190,000-square-foot structure will house all the college’s construction related programs.
It consists of a five-storey structural steel classroom tower highlighted with an atrium and a two-storey 100-metre-long structural steel, concrete, and precast low-rise structure for the trade shops. EllisDon is the design builder and Halsall Associates Ltd. is the structural consultant.
Approximately 1,500 tons of trusses, columns and other steel components will have been designed, fabricated and erected by Guelph-based Telco Steelworks by the time the project is finished.
“We are on a fast-track and the use of steel helps meet that schedule,” says Michael Leckman, principal, Diamond and Schmitt. “And constructing a building of this type with long spans consumes less embodied energy with composite steel.”
For example, while the 12-metre-long spans in the classrooms are somewhat long compared to standard academic buildings, they facilitated the design and construction of a space where the corridors have been minimized and a maximum use of classroom space has been achieved.
“It’s a very efficient use of a building,” he says.
In many of the workshop areas there are oversized 22-metre-long trusses which give those areas a nine-metre-height space compared to the seven-metre clearance the college had originally wanted.
“We recommended the extra height to support possible needed expansion in the future,” explains Leckman.
“The trade shop building actually showcases three different framing approaches,” says Tom Stevens, shareholder, Halsall Associates.
The central section is conventional cast-in-place concrete slabs supported by reinforced concrete beams and columns, while the floor framing on the west side consists primarily of 800 deep precast double-tees’s supported by reinforced concrete beams and columns.
The floor framing for the mezzanines on the east side are composite concrete slab and steel girders and purlins.
Most of the roof structure is steel decking supported by structural steel beams and steel joists, says Stevens.
It isn’t just the trusses and other steel supports which are being utilized to meet the dual scheduling and sustainability objectives.
Another feature is the centre’s insulated steel wall panel system comprised of approximately 1,060 individual panels. It will serve as both the exterior cladding and the interior finish.
“It is important to note the panels have an R30 insulation value,” says Leckman.
Manufactured by Vicwest Steel, the four-inch-thick panels will extend the full height of each floor and will be married with the punched window system. “We will be right behind the window contractor,” says Victor Da Rosa, sales manager for Ritz Metals, the panel subcontractor.
While the installation will be fairly straightforward, it won’t be without its challenges.
Because of the centre’s modular-style construction, the panels come in 24- 30- and 42-inch widths and they will require some adjustment, says Da Rosa, who expects the work to take about 40 days to complete.
Apart from the innovative use of steel, the project is unusual for the array of sustainability features that will be incorporated into the centre.
They include a five-storey bio-wall in the atrium, a storm-water recovery system, and a green roof to name just a few.
“This is not like anything I’ve seen in my working life,” says EllisDon construction manager Rocco Sala in referring to the centre’s features and design.
The fast paced schedule has required a lot of sequential tendering and some compromises from the subcontractors, he says.
“We’re already telling the finishing trades they better be prepared to do double shifts.”
| MOST POPULAR STORIES |
- How to suspend a 13-storey tower over a century-old four-storey structure
- Toronto Maple Leaf Gardens time capsule included construction details of arena
- Harley Davidson to roar into Quebec, with $15-million franchise headquarters under construction
- Steel hurdles for Aga Khan Museum build
- Caterpillar dispute a factor in CAW-CEP union merger talks
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 326 projects with a total value of $2,707,501,216 that Reed Construction Data Building Reports reported on Friday.
$800,000,000 Waterloo Reg ON Prebid
$235,700,000 Clarington ON Negotiated
CONDOMINIUM APARTMENT BUILDING
$87,000,000 North York ON CANCELLED/ DEFERRED
| CURRENT STORIES |
- National Research Council web wind tool helps with roof design
- Carillion Canada progresses on Ontario Coroner’s building in Toronto
- Benson Steel faces transport challenge on Toronto Yorkdale Mall construction project
- Knowing the bid rules essential for contractor success
- GDP down 0.1 per cent in November: Statistics Canada
- Ontario labour blitz to focus on musculoskeletal disorders
- Brazilian officials allege illegal construction in Rio de Janeiro high-rise building collapse
- Keeping it local in Lonsdale
- "Jobless boom" hits Saskatchewan
- Transmission line will generate shortages
- Fate of glass bridge not yet decided
- Why 45 days are important in the Builders Lien Act
- Construction and design modifications can promote elderly independence
- Inspired thinking highlights this year's Buildex Vancouver
- Industry to discuss changes in procurement
- The Living Building Challenge
- Getting a bigger bang with Building Information Modeling
- Come Say Hello to the Journal of Commerce
- Construction industry safety myths debunked in seminar
- A look at the challenges of smart structural reconstructions
- A look at the challenges of smart structural reconstructions
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 2) (January 12, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 1) (January 11, 2012)
- More








