March 26, 2010
FEATURE | Sewer and Watermain
Georgina, Ontario anticipates growth with sewer, road expansion
$47 million project is one of the biggest yet
It will be a beehive of construction activity in the Keswick area later this year when one of the largest infrastructure projects ever in the Town of Georgina gets underway.
New planned growth is the driving force behind a $47-million watermain/forcemain/road-widening project. Construction will start in the spring almost immediately after the tender award has been announced by the Region of York, says regional project manager Ben Pressman.
“It just makes sense to do everything at once,” says Pressman in explaining the decision to combine all three segments into one contract.
The project will take well into 2012 to complete and will be overseen by one contractor rather than divided into several phases, says Pressman.
Open-cut construction will be used to install a seven-kilometre 750-mm concrete pressure water main from the Georgina water treatment plant south to the Keswick Reservoir, just off Ravenshoe Road. A small 1.4 km portion of the watermain was installed last year.
The project will also include the installation of twin 6.4-kilometre-long, 400-mm forcemains which will link the Joe Dales pumping station to the Keswick Water Pollution Control plant. While there will be some installation along Ravenshoe Road and some side streets, the primary route of the water and forcemains will be adjacent Woodbine Avenue.
As the pipes are being installed, the contractor will also be doing the preparation work for a major expansion of Woodbine Avenue from three to five lanes from just north of Ravenshoe Road to Morton Avenue. The road work will also include widening the Maskinonge River Bridge from three to five lanes, with the addition of two bike lanes and a sidewalk, says Pressman.
While the terrain is fairly flat with few environmental constraints, determining the most appropriate method of installing the pipes across the river was one of the major design challenges.
Geotechncial and hydro geological investigations revealed the soils near the river were extremely poor consisting of layered silt and silty clay, says Mark Tarras, partner, the Municipal Infrastructure Group Ltd., the project’s consulting engineers.
“We considered crossing the river either via a tunnel or directional drilling. However that was ruled out once we considered the potential of flowing conditions in the tunnel option and the potential for frac-out with directional drilling,” he says.
The solution was to suspend the pipes from the underside of the bridge expansion between the girders. Each pipe will be insulated, heat traced monitored for temperature and protected with a steel casing. Expansion joints will allow the pipes to expand and deflect, says Tarras.
| MOST POPULAR STORIES |
- How to suspend a 13-storey tower over a century-old four-storey structure
- Toronto Maple Leaf Gardens time capsule included construction details of arena
- Harley Davidson to roar into Quebec, with $15-million franchise headquarters under construction
- Steel hurdles for Aga Khan Museum build
- Caterpillar dispute a factor in CAW-CEP union merger talks
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 326 projects with a total value of $2,707,501,216 that Reed Construction Data Building Reports reported on Friday.
$800,000,000 Waterloo Reg ON Prebid
$235,700,000 Clarington ON Negotiated
CONDOMINIUM APARTMENT BUILDING
$87,000,000 North York ON CANCELLED/ DEFERRED
| CURRENT STORIES |
- National Research Council web wind tool helps with roof design
- Carillion Canada progresses on Ontario Coroner’s building in Toronto
- Benson Steel faces transport challenge on Toronto Yorkdale Mall construction project
- Knowing the bid rules essential for contractor success
- GDP down 0.1 per cent in November: Statistics Canada
- Ontario labour blitz to focus on musculoskeletal disorders
- Brazilian officials allege illegal construction in Rio de Janeiro high-rise building collapse
- Keeping it local in Lonsdale
- "Jobless boom" hits Saskatchewan
- Transmission line will generate shortages
- Fate of glass bridge not yet decided
- Why 45 days are important in the Builders Lien Act
- Construction and design modifications can promote elderly independence
- Inspired thinking highlights this year's Buildex Vancouver
- Industry to discuss changes in procurement
- The Living Building Challenge
- Getting a bigger bang with Building Information Modeling
- Come Say Hello to the Journal of Commerce
- Construction industry safety myths debunked in seminar
- A look at the challenges of smart structural reconstructions
- A look at the challenges of smart structural reconstructions
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 2) (January 12, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 1) (January 11, 2012)
- More








