February 11, 2010
PENN-CO CONSTRUCTION
The new treatment plant at Kingfisher Lake First Nation is situated beside the plant it replaced.
FOCUS | Water & wastewater
Kingfisher Lake residents become crew on water treatment plant project
Clean drinking water and efficient wastewater treatment would seem to be a given in an industrialized country like Canada, but for those in the far north it’s a different story.
That’s why the opening of the Kingfisher Lake First Nation’s water treatment plant last year marked a giant step for the tiny community of less than 500 people north of Thunder Bay and closer to the Manitoba border than any other Ontario town.
While the plant itself is a fairly simple construction and the conventional treatment technology a common method, the project was not without a few challenges, said Ran Reimer, the project manager for Penn-Co Construction of Manitoba which specializes in remote installations.
“There’s no road in,” he says. “So everything had to be trucked in during the winter (when the lakes freeze) and we had to anticipate every last nut and bolt we would need.”
As it was, the project only had a couple of minor glitches which set the schedule back but it was completed in a year almost exactly, he said.
Because of the community’s relative isolation, the water treatment plant had to be almost bulletproof to run since getting skilled technical help on a moment’s notice is always going to be an issue.
“There are still chemicals to be mixed and applied but a conventional system is pretty basic and there are millions of them in use,” he said, comparing the technology to sand and membrane-style treatment facilities.
With three Penn-Co employees directing the work, the local community provided the labour starting in April 2008.
“First thing we did was blast the rock for the building,” said Reimer. “It’s all bedrock, there so we had no choice.”
Chief James Mamakwa said the blasting was a popular community event and not an everyday occurrence.
“It was pretty exciting,” he laughed.
“But they did a good job covering the ground with blast mats, so things didn’t go everywhere.”
From there construction went on as normal, though as Mamakwa notes there were some challenges getting the concrete floor to be seamless.
The building was a simple steel frame structure with steel walls, said Reimer, and because the new plant was built beside the existing plant, little in the way of new blasting to lay pipes was needed.
“We had a bit to do for the tie-in but not much,” he explained.
In fact, Chief Mamakwa said the community tried to get additional pipes laid but were unable to get funding and support.
“Even with this plant, only 50 per cent of the community has piped-in water,” he says. “Some 50 per cent still have it trucked in and that’s very expensive.”
He says the issue is that laying pipe will involve a lot of blasting because the community is built on bedrock. That’s the only way to protect it from the constant minus 25C temperatures in winter.
In 2001 a survey of the community found it in dire need of water treatment, with 202 people using piped water and 189 having trucked-in water and four having no water at all.
Similar numbers were found with sewage treatment, making the community a high priority target for federal government funding for upgrades.
Indian and Northern Affairs Canada provided Kingfisher Lake First Nation with $8.3 million for the new plant. The First Nation managed planning, design, construction and commissioning of the facility. Changes to operations and processes were also implemented. The new facility currently has excess capacity which will enable it to meet future water demands. “This will allow us to at least sustain our community and even grow,” said Mamakwa.
The community itself dates back several hundred years and used to trade at the Hudson’s Bay Company outpost at Big Beaver House which is about 12 kilometres south. The post was established in 1808.
Things went mostly according to plan and there were only a couple of items that needed to be flown in.
“There’s always something,” he recalled.
“But it’s not as isolated as it seems and it’s a really nice community up there. The labour force was good and they were amicable and willing and ready to work.”
| MOST POPULAR STORIES |
- How to suspend a 13-storey tower over a century-old four-storey structure
- Toronto Maple Leaf Gardens time capsule included construction details of arena
- Harley Davidson to roar into Quebec, with $15-million franchise headquarters under construction
- Steel hurdles for Aga Khan Museum build
- Caterpillar dispute a factor in CAW-CEP union merger talks
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 326 projects with a total value of $2,707,501,216 that Reed Construction Data Building Reports reported on Friday.
$800,000,000 Waterloo Reg ON Prebid
$235,700,000 Clarington ON Negotiated
CONDOMINIUM APARTMENT BUILDING
$87,000,000 North York ON CANCELLED/ DEFERRED
| CURRENT STORIES |
- National Research Council web wind tool helps with roof design
- Carillion Canada progresses on Ontario Coroner’s building in Toronto
- Benson Steel faces transport challenge on Toronto Yorkdale Mall construction project
- Knowing the bid rules essential for contractor success
- GDP down 0.1 per cent in November: Statistics Canada
- Ontario labour blitz to focus on musculoskeletal disorders
- Brazilian officials allege illegal construction in Rio de Janeiro high-rise building collapse
- Keeping it local in Lonsdale
- "Jobless boom" hits Saskatchewan
- Transmission line will generate shortages
- Fate of glass bridge not yet decided
- Why 45 days are important in the Builders Lien Act
- Construction and design modifications can promote elderly independence
- Inspired thinking highlights this year's Buildex Vancouver
- Industry to discuss changes in procurement
- The Living Building Challenge
- Getting a bigger bang with Building Information Modeling
- Come Say Hello to the Journal of Commerce
- Construction industry safety myths debunked in seminar
- A look at the challenges of smart structural reconstructions
- A look at the challenges of smart structural reconstructions
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 2) (January 12, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 1) (January 11, 2012)
- More