February 11, 2010
REGION OF PEEL
Expansion of the Clarkson Wastewater Treatment Plant in south Mississauga will occur while the plant is still in operation.
FOCUS | Water & wastewater
Peel Region begins expansion of Clarkson Wastewater Treatment Plant
With the construction completion of a 2.2-kilometre-long outfall tunnel into Lake Ontario in November, Peel Region is now proceeding with a massive three-year $160-million expansion of its Clarkson Wastewater Treatment Plant in south Mississauga.
Needed to meet rapid residential growth occurring west of the Credit River in Mississauga and Brampton, the expansion will increase the plant’s treatment capacity from 200 to 350 megalitres a day, says William Fernandes, the region’s capital works manager for wastewater treatment.
Some of the components of the project include the construction of primary tanks, aeration tanks, final tanks, and the installation of maze equipment, plus associated piping and electrical connections. There will be at least nine below-ground concrete tanks.
As the plant is located on a large property on the north side of Lakeshore Road, there is plenty of space for the expansion which will occur on the northeast quadrant.
Earlier this winter, earthworks and site preparation by Woodbridge-based Gentile Contracting Ltd. got underway. The site work includes the creation of berms for a community recycling centre which will be built on the southwest corner of the sprawling property.
The recycling centre is not connected with the operation of the plant and will be built under a totally separate contract.
However, it is a regional facility and locating it there saves the region land acquisitions costs had it be built somewhere else, explains Fernandes.
Design work will start this spring and there will be plenty of upcoming opportunities for the construction industry. To make the project more manageable, obtain more competitive bids and to accommodate trades with different specialities, it will be divided into at least four and possibly five contracts, he says.
“There will be quite a bit of mechanical and civil work needed.”
Construction will ramp up later this year, with the peak of the work lasting from about mid-2011 until about the same period in 2012. With commissioning and other final work, it won’t be until 2013 before the project is totally complete and the enlarged facility operational, says Fernandes.
Although the Clarkson plant is situated in what is primarily an industrial area, precautions will still have to be taken to minimize construction noise and odour exposure to nearby residential areas, he points out.
“The major complications will be ties-in with existing sewer lines. We can’t stop the plant. It has to be kept operating at all times,” says Fernandes, when asked about the main challenges.
The need for the expansion was first identified in a waste and wastewater master plan the region produced in the late 1990s. But that growth couldn’t proceed before the outfall tunnel was in place to accommodate the treated sewage.
As the tunnel was being built by general contractor C&M McNally Engineering Corp, the environmental assessment for the expansion was conducted, says Fernandes.
“Everything fit to a T.”
| MOST POPULAR STORIES |
- How to suspend a 13-storey tower over a century-old four-storey structure
- Toronto Maple Leaf Gardens time capsule included construction details of arena
- Harley Davidson to roar into Quebec, with $15-million franchise headquarters under construction
- Steel hurdles for Aga Khan Museum build
- Caterpillar dispute a factor in CAW-CEP union merger talks
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 326 projects with a total value of $2,707,501,216 that Reed Construction Data Building Reports reported on Friday.
$800,000,000 Waterloo Reg ON Prebid
$235,700,000 Clarington ON Negotiated
CONDOMINIUM APARTMENT BUILDING
$87,000,000 North York ON CANCELLED/ DEFERRED
| CURRENT STORIES |
- National Research Council web wind tool helps with roof design
- Carillion Canada progresses on Ontario Coroner’s building in Toronto
- Benson Steel faces transport challenge on Toronto Yorkdale Mall construction project
- Knowing the bid rules essential for contractor success
- GDP down 0.1 per cent in November: Statistics Canada
- Ontario labour blitz to focus on musculoskeletal disorders
- Brazilian officials allege illegal construction in Rio de Janeiro high-rise building collapse
- Keeping it local in Lonsdale
- "Jobless boom" hits Saskatchewan
- Transmission line will generate shortages
- Fate of glass bridge not yet decided
- Why 45 days are important in the Builders Lien Act
- Construction and design modifications can promote elderly independence
- Inspired thinking highlights this year's Buildex Vancouver
- Industry to discuss changes in procurement
- The Living Building Challenge
- Getting a bigger bang with Building Information Modeling
- Come Say Hello to the Journal of Commerce
- Construction industry safety myths debunked in seminar
- A look at the challenges of smart structural reconstructions
- A look at the challenges of smart structural reconstructions
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 2) (January 12, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 1) (January 11, 2012)
- More








