DCN ARCHIVES

August 1, 2007

Architect Peter Cook shows off the model of what The Chatham Capitol Theatre will look like when it's completed. Another $2.8 million needs to be raised before the final phase of the project can begin. That phase is then expected to take about 18 months to complete.

YVONNE BENDO

Architect Peter Cook shows off a model of the Chatham Capitol Theatre. Another $2.8 million needs to be raised before the final phase of the project, which is expected to take about 18 months, can begin.

Restoration

Architect strikes balance between restoration and modernization of Chatham theatre

CHATHAM

Architect Peter Cook understands there’s a delicate balance in transforming an historic theatre into a modern performing arts centre.

“There’s an enthusiasm behind this project to take the effort to restore it properly and to make a statement of the building as a representation of an historical artifact, as well as a vibrant living organism,” Cook says, of the Chatham Capitol Theatre restoration project.

Constructed in 1930, the King Street West theatre was formerly a movie house before its doors were boarded in 1992.

A couple of years later a group of concerned citizens formed The Chatham Capitol Theatre Association, sparing the theatre from demolition and beginning the restoration effort.

Virtually, the entire inside has been stripped back to its shell.

“The infrastructure is here ... and there’s a tremendous sense of style to the building which has been augmented and developed further,” the architect says.

To be economically viable as a theatre, 1,200 seats are required. That meant constructing a 400-seat balcony and raft slab foundation was installed for support.

“It’s a two-foot thick slab of concrete that runs the size of the basement under the balcony.

“All the weight of the balcony and the columns are offset by the dispersion of that volume of space that the raft slab takes up,” the architect explains.

The bonus for the theatre is that it gains a large basement, which can be used as another lounge area.

Poor soil conditions, partly a result of being located about 200 metres from the Thames River, created some challenges.

Helical piles were required since the soil wasn’t solid below nine feet, Cook says.

“Trying to drive piles adjacent or near an old building of this nature runs a lot of risk. With the vibrations and impact, the brickwork can be damaged. The helical piles don’t have that risk.”

Because they’re augered down about 40 feet, he says, they can be installed inside the building as well as outside, which is what was done in this case to “support the perimeter walls of the existing building while we were excavating and putting in some of the basement space.”

David Hannivan of  Toronto-based Hannivan & Company Ltd. was key  in providing the artistic insights in creating a space and a quality of space that's reflective of the style and period of the building

David Hannivan, of Toronto-based Hannivan & Company Ltd., provided artistic insights that helped create a space that reflects the style and period of the building.

A number of consultants have been involved in the project thus far, including decorative restorator David Hannivan of Toronto-based Hannivan & Company Ltd.

“Hannivan has been just tremendous in providing the artistic insights in creating a space and a quality of space that’s reflective of the style and period of the building,” Cook says.

The historic restoration of the interior is very time-consuming and would have been too costly, if not for training funds made available through Human Resources Development Canada, explains project manager Bob Fox.

Bob Fox, project manager for the restoration of Chatham's Capitol Theatre, shows how craftsmen experimented with different techniques to find the right finish.

YVONNE BENDO

Bob Fox, project manager of Chatham's Capitol Theatre restoration, shows how craftsmen experimented with different techniques to find the right finish.

He says there’s a shortage of skilled people to do the restoration work and through the HRDC program, Hannivan has trained more than 150 people in restorative plastering and painting.

Fundraising is a major reason for the project’s slow pace, Fox admits.

Although it’s been a work-in-progress for more than 10 years, he says another $2.8 million needs to be raised before the last phase of construction can begin.

“It’s the shortfall between the financing we have available and being able to perform the balance of the work,” Fox says.

When completed, the project will ring in at a cost of about $14 million.

The front seating area, as well as the 70-by-40 foot stage and backstage — including a fly-tower — have yet to be constructed.

Cook explains the fly-tower “is the whole high structure which allows scenery and backdrops and components of the stage performance to be flown or lifted up, out of the view of the audience; and other components to be brought in.

“It allows for quick set changes and different lighting effects to take place.”

It’s so important that Cook says some acts won’t perform in a facility that doesn’t have a fly-tower.

“For us to build a 1,200-seat theatre with a stage of this size and not to put a fly-tower on it would put the building out of balance ... you would be missing something, like buying a car that only has three wheels,” Cook says.

Print | Email | Comment

MOST POPULAR STORIES
TODAY’S TOP CONSTRUCTION PROJECTS

These projects have been selected from 326 projects with a total value of $2,707,501,216 that Reed Construction Data Building Reports reported on Friday.

RAPID TRANSIT SYSTEM UPGRADES

$800,000,000 Waterloo Reg ON Prebid

SOLID WASTE FACILITY

$235,700,000 Clarington ON Negotiated

CONDOMINIUM APARTMENT BUILDING

$87,000,000 North York ON CANCELLED/ DEFERRED

Daily Top 10

CURRENT STORIES
ALEX’S ECONOMICS BLOG

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.

TODAY’S TOP JOBS

Chief/Senior Estimator
Ontario-Brampton

Inside Sale Representative
Ontario-Markham

Branch Manager
British Columbia-Surrey

Contracts Estimator & Project Coordinator
Ontario-Etobicoke

Structural Engineer
Ontario-Toronto

Manager Maintenance & Engineering Services
Ontario-Oakville

Supervisor
Ontario-Etobicoke

Estimator
Ontario-Etobicoke

Estimating Coordinator (10-804)
Alberta-Edmonton

Project Administrator
Saskatchewan-Saskatoon

More jobs 

myJobsite.ca

Your gateway to
the top careers
in construction
and design