January 19, 2007
Going through a legal battle can be a costly way to settle disputes arising from issues related to minor contractual issues and non-compliance with bid submissions.
Tendering
Non-compliance a sticking point in legal battles
Litigation an expensive way to settle issues
In 1981, the Supreme Court of Canada’s decision in Ontario v. Ron Engineering changed the legal landscape of invitations to tender.
In that case, a bidder was prevented from revoking a bid on the grounds that the submission featured an omission. In the ensuing 25 years, a significant number of court cases have hinged on minor contractual issues, with compliant but failed bidders suing owners for lost profits because the winning bidder could be shown to be non-compliant.
“Most construction litigation is extremely expensive, but it doesn’t cost much to be heard in these cases,” says Christopher Hirst, a partner with Vancouver’s Alexander, Holburn, Beaudin & Lang.
“The litigation usually involves only a few small points, and the trial might last a week, so the damages you might be entitled to could be very significant compared to the cost of the trial.”
"Compliant in Canada means 100 per cent compliant to the words in the invitation to bid..."
Robert Worthington
Worthington and Associates
But there are exceptions.
The case of Double N Earthmovers Ltd. v. City of Edmonton was heard by the Supreme Court of Canada last summer.
Double N initially sued the City of Edmonton in 1986 because the city accepted a non-compliant bid from rival firm, Sureway Construction.
Although Sureway’s bid was lowest, the contract specified that all equipment used in fulfilling the contract must be from 1980 or newer.
The company’s equipment was later shown to be a 1979 model.
“Sometimes things move very slowly,” says Samuel Kravinchuk, a lawyer representing Double N. “It’s an embarrassment for my client.”
In other cases, a tiny omission provides a legal focal point. In Johnson’s Construction Ltd. v. Newfoundland (2000), The Newfoundland Supreme Court ruled that an owner had no right to accept a bid that was missing one unit price, because the owner had made this a condition of acceptance.
Owners are attempting to sidestep such legal perils by carefully wording their tender documents, says Robert Worthington, president of Surrey, BC law firm Worthington and Associates, and author of the Purchasing Law Handbook.
“Compliant in Canada means 100 per cent compliant to the words in the invitation to bid, both for the bidder and for the owner in the evaluation process. Some owners try to expressly claim the right to waive non-compliance, but isn’t that contrary to the rules?”
Worthington notes some large companies no longer accept competitive bids because the legal risk of a lawsuit arguing non-compliance is too great.
“A Shell or Imperial Oil working on a big Oil Sands project knows what it wants and knows what the price should be and avoids competitive bidding altogether. They’re just saying ‘we don’t want to get involved in these lawsuits.’”
Worthington says the law won’t stand still. “Some people will say they liked the rules when John A. MacDonald was a kid, but an appeals court will alter them. Although people apply constantly, the Supreme Court of Canada doesn’t hear many cases, but will step in every few years and restate the law, adjusting it but not reversing it.”
A decision in the Double N case is expected soon.
| MOST POPULAR STORIES |
- Steel hurdles for Aga Khan Museum build
- How to suspend a 13-storey tower over a century-old four-storey structure
- Benson Steel faces transport challenge on Toronto Yorkdale Mall construction project
- York Region, Ontario approves subway construction expenditures
- Bidding closes for Toronto 2015 Pan Am games venues
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 239 projects with a total value of $1,872,783,897 that Reed Construction Data Building Reports reported on Tuesday.
$59,000,000 Milton ON Prebid
$50,000,000 Metro Toronto Reg ON Tenders
$49,375,000 Toronto ON Prebid
| CURRENT STORIES |
- Toronto Construction Association presents ‘Best of the Best’ awards
- Interior floor care a major consideration in condo maintenance
- Brazil World Cup venue workers threaten strike
- Construction plans heated up in December 2011: Statistics Canada
- Canada about to fall to second in economic growth among the G7
- Thunder Bay, Ontario considers $40-million capital budget
- North Vancouver condos are First Place
- $2 billion oilsands expansion gets the green light
- Whistler asphalt plant operator wins court battle
- Research council's web wind tool helps with roof design
- Exploring the Canadian identity
- Immigration stream would be welcome
- Saskatchewan mayors want cash
- Yukon's first LEED structure earns its certification
- Co-operation planned on codes and standards
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canada’s labour market flat in January but U.S. on a roll (February 3, 2012)
- Canada’s leading indicator series continued to charge ahead in December (January 23, 2012)
- 2012 holds promise but there’s no denying the uncertainty (part 2) (January 12, 2012)
- More